Ricine Banner
File #: 0641-19    Version: A Name: Subject: Communication from Alder Tate ll submitting Change Order No. 1 on Contract 20180123, State Street Lift Bridge - Electrical Updates, Faith Technologies, Inc., contractor.
Type: Communication Status: Passed
File created: 5/23/2019 In control: Public Works and Services Committee
On agenda: 6/4/2019 Final action: 6/4/2019
Title: Subject: Communication from Alder Tate ll submitting Change Order No. 1 on Contract 20180123, State Street Lift Bridge - Electrical Updates, Faith Technologies, Inc., contractor. Recommendation of the Public Works and Services Committee on 05-28-19: That Change Order No. 1 on Contract 20180123, State Street Lift Bridge - Electrical Updates, Faith Technologies, Inc., contractor, be approved in the amount of $35,820.00. Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 40402-57545, Bridges-State. Fiscal Note: Funds are available as herein delineated.
Sponsors: John Tate II
Attachments: 1. 0641-19 CO1 Contract 20180123.pdf, 2. #0641-19 Resolution

Title

Subject: Communication from Alder Tate ll submitting Change Order No. 1 on Contract 20180123, State Street Lift Bridge - Electrical Updates, Faith Technologies, Inc., contractor.

 

Recommendation of the Public Works and Services Committee on 05-28-19: That Change Order No. 1 on Contract 20180123, State Street Lift Bridge - Electrical Updates, Faith Technologies, Inc., contractor, be approved in the amount of $35,820.00.

 

Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 40402-57545, Bridges-State.

 

Fiscal Note:  Funds are available as herein delineated.