Title: Subject: Communication sponsored by Alder Levie, on behalf of Public Works, submitting Change Order No. 1 on Contract 20190017, 2019 CDBG Resurfacing, Payne & Dolan, Inc., contractor. Recommendation of the Public Works and Services Committee on 11-12-19: That Change Order No. 1 on Contract 20190017, 2019 CDBG Resurfacing, Payne & Dolan, Inc., contractor, be approved in the amount of $31,566.21. Further recommends that the below funding accounts be adjusted by the following amount: $48,345.00 - Org-Object 22640-57560, Sanitary Sewers ($ 7,736.53) - Org-Object 60484-57570, Storm Sewers ($17,500.81) - Org-Object 45040-57515, Sidewalk Replacement $ 8,458.55 - Org-Object 45040-57510, Curb & Gutter Replacement $31,566.21 - Total Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 1159-19 CO1 Contract 20190017, 2019 CDBG Resurfacing, Payne & Dolan.pdf, 2. #1159-19 Resolution

Title

Subject: Communication sponsored by Alder Levie, on behalf of Public Works, submitting Change Order No. 1 on Contract 20190017, 2019 CDBG Resurfacing, Payne & Dolan, Inc., contractor.

 

Recommendation of the Public Works and Services Committee on 11-12-19: That Change Order No. 1 on Contract 20190017, 2019 CDBG Resurfacing, Payne & Dolan, Inc., contractor, be approved in the amount of $31,566.21.

 

Further recommends that the below funding accounts be adjusted by the following amount:

 

 $48,345.00   - Org-Object 22640-57560, Sanitary Sewers

($  7,736.53)  - Org-Object 60484-57570, Storm Sewers

($17,500.81)  - Org-Object 45040-57515, Sidewalk Replacement

 $  8,458.55   - Org-Object 45040-57510, Curb & Gutter Replacement

 $31,566.21   - Total

 

Fiscal Note:  Funds are available as herein delineated.