Title
Subject: Communication sponsored by Alder Levie, on behalf of Public Works, submitting Change Order No. 1 on Contract 20190017, 2019 CDBG Resurfacing, Payne & Dolan, Inc., contractor.
Recommendation of the Public Works and Services Committee on 11-12-19: That Change Order No. 1 on Contract 20190017, 2019 CDBG Resurfacing, Payne & Dolan, Inc., contractor, be approved in the amount of $31,566.21.
Further recommends that the below funding accounts be adjusted by the following amount:
$48,345.00 - Org-Object 22640-57560, Sanitary Sewers
($ 7,736.53) - Org-Object 60484-57570, Storm Sewers
($17,500.81) - Org-Object 45040-57515, Sidewalk Replacement
$ 8,458.55 - Org-Object 45040-57510, Curb & Gutter Replacement
$31,566.21 - Total
Fiscal Note: Funds are available as herein delineated.