Title: Subject: Communication sponsored by Alder Tate ll, on behalf of Public Works, submitting a final payment: Contract 20190085, Library Entrance Door/Vestibule Replacement , Absolute Construction, contractor. Recommendation of the Public Works and Services Committee on 1-28-20: That the work done by Absolute Construction, under Contract 20190085, Library Entrance Door/Vestibule Replacement, be accepted and final payment authorized for a total contract amount of $113,800.00. Final Payment to include retainage. Fiscal Note: Contract was authorized under Resolution 0842-19, dated August 20, 2019. Contract 20180119, 2018 Sanitary Sewer Lining, Michels Corporation, contractor. Recommendation of the Public Works and Services Committee on 1-28-20: That the work done by Michels Corporation, under Contract 20180119, 2018 Sanitary Sewer Lining, be accepted and final payment authorized for a total contract amount of $1,235,619.33. Final Payment to include retainage. Fiscal Note: Contract w...
Attachments: 1. 0049-20 Final Payment Library, 2. 0049-20, Contract 20180119, 2018 Sanitary Sewer Lining, Michels Corporation, 3. 0049-20 Final Payment 2018 Sanitary Sewer Lining, 4. #0049- 20 Resolution

Title

Subject: Communication sponsored by Alder Tate ll, on behalf of Public Works, submitting a final payment:

 

Contract 20190085, Library Entrance Door/Vestibule Replacement , Absolute Construction, contractor.

 

Recommendation of the Public Works and Services Committee on 1-28-20: That the work done by Absolute Construction, under Contract 20190085, Library Entrance Door/Vestibule Replacement, be accepted and final payment authorized for a total contract amount of $113,800.00. Final Payment to include retainage.

 

Fiscal Note:  Contract was authorized under Resolution 0842-19, dated August 20, 2019.

 

 

Contract 20180119, 2018 Sanitary Sewer Lining, Michels Corporation, contractor.

 

Recommendation of the Public Works and Services Committee on 1-28-20: That the work done by Michels Corporation, under Contract 20180119, 2018 Sanitary Sewer Lining, be accepted and final payment authorized for a total contract amount of $1,235,619.33. Final Payment to include retainage.

 

Fiscal Note:  Contract was authorized under Resolution 0283-18, dated September 18, 2018.