File #: Res.15-0045    Version: A Name: Assessment Rates Established for 2015 Public Hearings for 2016 Construction of Portland Cement Concrete Paving and Curb and Gutter
Type: Resolution Status: Passed
File created: 2/3/2015 In control: City Attorney's Office
On agenda: Final action: 2/3/2015
Title: Assessment Rates Established for 2015 Public Hearings for 2016 Construction of Portland Cement Concrete Paving and Curb and Gutter Resolved, that the proposed special assessment rates for public hearings in 2015 for 2016 construction for Portland Cement concrete paving and curb and gutter are as follows: Residential Paving (7-Inch) - 14' Flange to Flange - $33.00/Front Foot Residential Paving (7-Inch) - 26' Flange to Flange - $65.00/Front Foot Residential Paving (7-Inch) - 30' Flange to Flange - $67.00/Front Foot Residential Paving (7-Inch) - 32' Flange to Flange - $70.00/Front Foot Residential Paving (7-Inch) - 46' Flange to Flange - $95.00/Front Foot Commercial Paving (8-Inch) - 32' Flange to Flange - $75.00/Front Foot Industrial Paving (9-Inch) - 32' Flange to Flange - $85.00/Front Foot Industrial Paving (9-Inch) - 42' Flange to Flange - $100.00/Front Foot Industrial Paving (9-Inch Doweled) - 44' Flange to Flange - $115.00/Front Foot Industrial Paving (10-Inch Doweled) - ...
Sponsors: Jim Kaplan
Related files: 15-00082
Sponsor
Alderman Kaplan
 
Title
Assessment Rates Established for 2015 Public Hearings for 2016 Construction of Portland Cement Concrete Paving and Curb and Gutter
 
Resolved, that the proposed special assessment rates for public hearings in 2015 for 2016 construction for Portland Cement concrete paving and curb and gutter are as follows:
 
Residential Paving (7-Inch) - 14' Flange to Flange - $33.00/Front Foot
 
Residential Paving (7-Inch) - 26' Flange to Flange - $65.00/Front Foot
 
Residential Paving (7-Inch) - 30' Flange to Flange - $67.00/Front Foot
 
Residential Paving (7-Inch) - 32' Flange to Flange - $70.00/Front Foot
 
Residential Paving (7-Inch) - 46' Flange to Flange - $95.00/Front Foot
 
Commercial Paving (8-Inch) - 32' Flange to Flange - $75.00/Front Foot
 
Industrial Paving (9-Inch) - 32' Flange to Flange - $85.00/Front Foot
 
Industrial Paving (9-Inch) - 42' Flange to Flange - $100.00/Front Foot
 
Industrial Paving (9-Inch Doweled) - 44' Flange to Flange - $115.00/Front Foot
 
Industrial Paving (10-Inch Doweled) - 44' Flange to Flange - $125.00/Front Foot
 
New Curb & Gutter (30-Inch) - 7" Pavement - $22.00/Front Foot
 
New Curb & Gutter (30-Inch) - 8" Pavement - $24.00/Front Foot
 
New Curb & Gutter (30-Inch) - 9" Pavement - $26.00/Front Foot
 
Sewer (6") & Water (1") Services - $10,500.00/Each
 
Sewer (6") & Water (2") Services - $12,000.00/Each
 
Alley Paving (10 Foot ROW) - 7" Pavement - $35.00/Front Foot
 
Alley Paving (11-15 Foot ROW) - 7" Pavement - $45.00/Front Foot
 
Alley Paving (16-20 Foot ROW) - 7" Pavement - $55.00/Front Foot
 
Alley Paving (21-25 Foot ROW) - 7" Pavement - $65.00/Front Foot
 
Further resolved, that these special assessment rates become effective upon passage of the Common Council for all preliminary resolutions.
 
These rates apply to all streets, regardless of width, unless the actual construction cost is less, then the front foot cost shall be reduced accordingly.
 
Fiscal Note: These rates are established so that the abutting property owner pays 100% of the cost of such street improvements.