File #: Res.06-7145    Version: A Name: CONDITIONAL USE PERMIT FOUR GASLIGHT DRIVE, GASLIGHT POINTE DEVELOPMENT
Type: Resolution Status: Passed
File created: 7/18/2006 In control: City Attorney's Office
On agenda: Final action: 7/18/2006
Title: CONDITIONAL USE PERMIT FOUR GASLIGHT DRIVE, GASLIGHT POINTE DEVELOPMENT RESOLVED, that the the plans submitted by New England Builders for Gaslight Pointe Associates, LLC., seeking a conditional use permit in the planned development of Gaslight Pointe to construct a four-story residential condominium at Four Gaslight Drive be approved, subject to the following conditions: a. That the plans presented to the Plan Commission on July 12, 2006 be approved subject to the conditions contained herein: b. That the following be accomplished prior to the issuance of a building permit; 1. Submit site, lighting, and landscaping plans to the Downtown Area Design Review Commission for review and consultation. 2. Submit site, lighting and landscaping plans to the Director of City Development for review, an approval following Downtown Area Design Review Commission’s review and consultation. 3. Submit for approval drainage plans to the City Engineer, and utility plans to the Raci...
Sponsors: Gregory Helding
Related files: 06-2206

Sponsor

Alderman Helding

 

Title

CONDITIONAL USE PERMIT FOUR GASLIGHT DRIVE, GASLIGHT POINTE DEVELOPMENT

 

 

RESOLVED, that the the plans submitted by New England Builders for Gaslight Pointe Associates, LLC., seeking a conditional use permit in the planned development of Gaslight Pointe to construct a four-story residential condominium at Four Gaslight Drive be approved, subject to the following conditions:

 

a.  That the plans presented to the Plan Commission on July 12, 2006 be approved subject to the conditions contained herein:

 

b.  That the following be accomplished prior to the issuance of a building permit;

 

    1.  Submit site, lighting, and landscaping plans to the Downtown Area Design Review Commission for review and consultation.

 

    2.  Submit site, lighting and landscaping plans to the Director of City Development for review, an approval following Downtown Area Design Review Commission’s review and consultation.

 

    3.  Submit for approval drainage plans to the City Engineer, and utility plans to the Racine Water and Waste Water Utilities.

 

c.  That the following be accomplished prior to the issuance of occupancy permits;

 

     1.  Install all landscaping as illustrated in the approved plans or submit a letter of credit equal to the value of the approved plan.  In such latter case, landscaping shall be completed within six months of the date an occupancy permit was obtained.

 

    2.  All drive and walk areas shall be have final pavement or a letter of credit shall be provided equal to the value of the paving.  In such latter case, final paving shall be completed within six months of the date an occupancy permit was obtained.

 

    3.  All appropriate documents as outlined by Section 114-181 of the City of Racine Municipal Code shall be filed by the applicant, or its agent, with the Racine County Register of Deeds.  Prior to recording, all documents shall be submitted to the Director of City Development for review and approval.

 

d.  That the project density, floor area ratio, units count, yard areas and building height be complied with as presented in the approved plans.

 

e.  That any driveway openings and closures are subject to the review and approval of the Commissioner of Public Works.

 

f.  That all codes and ordinances be complied with and all permits acquired.

 

k.  That no minor changes be made from the conditions of this permit without the approval of the Plan Commission and no major changes be made from the conditions of this permit without the approval of the Common Council.

 

l.  That this permit is subject to Plan Commission review for compliance with the listed conditions.

 

 

FISCAL NOTE:  N/A