File #: Res.09-1598    Version: A Name: Change Order No 1 on Contract 10-09 (K9-010), 2009 Sidewalk Construction, Phase 1, Sam's Cement, contractor, be approved
Type: Resolution Status: Passed
File created: 9/15/2009 In control: City Attorney's Office
On agenda: Final action: 9/15/2009
Title: Change Order No 1 on Contract 10-09 (K9-010), 2009 Sidewalk Construction, Phase 1, Sam's Cement, contractor, be approved Resolved, that Change Order No. 1 on Contract 10-09 (K9-010), 2009 Sidewalk Construction, Phase I, Sam's Cement, contractor, as submitted, be approved in the deduct amount of $7,589.26. Fiscal Note: Change Order No. 1 will result in a decrease in contract price.
Sponsors: Gregory Helding
Related files: 09-4096
Sponsor
Alderman Helding
 
Title
Change Order No 1 on Contract 10-09 (K9-010), 2009 Sidewalk Construction, Phase 1, Sam's Cement, contractor, be approved
 
Resolved, that Change Order No. 1 on Contract 10-09 (K9-010), 2009 Sidewalk Construction, Phase I, Sam's Cement, contractor, as submitted, be approved in the deduct amount of $7,589.26.
 
Fiscal Note:  Change Order No. 1 will result in a decrease in contract price.