Title: CHANGE ORDER CONCRETE STREET RECONSTRUCTION AND PAVING RESOLVED, that Change Order No. 3 on Contract 24-06 (K6-025), Concrete Street Reconstruction and Paving, Milwaukee General Construction Co., Inc., contractor, as submitted, be approved in the amount of $4,736.00. FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 986.908.5020, Concrete Pavement Replacement, Miscellaneous Locations. FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-2403

Sponsor

Alderman Hart

 

Title

CHANGE ORDER CONCRETE STREET RECONSTRUCTION AND PAVING

 

 

RESOLVED, that Change Order No. 3 on Contract 24-06 (K6-025), Concrete Street Reconstruction and Paving, Milwaukee General Construction Co., Inc., contractor, as submitted, be approved in the amount of $4,736.00.

 

FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 986.908.5020, Concrete Pavement Replacement, Miscellaneous Locations.

 

 