File #: 0966-19    Version: A Name: Subject: Communication sponsored by Alder Tate ll, on behalf of Engineering, submitting Change Order No. 2 on Contract 20170006 - 2017 Circuit Replacement - Wisconsin Avenue, Wil-Surge Electric, Inc., contractor.
Type: Communication Status: Passed
File created: 8/21/2019 In control: Public Works and Services Committee
On agenda: 9/3/2019 Final action: 9/3/2019
Title: Subject: Communication sponsored by Alder Tate ll, on behalf of Engineering, submitting Change Order No. 2 on Contract 20170006 - 2017 Circuit Replacement - Wisconsin Avenue, Wil-Surge Electric, Inc., contractor. Recommendation of the Public Works and Services Committee on 08-27-19: That Change Order No. 2 on Contract 20170006, 2017 Circuit Replacement - Wisconsin Avenue, Wil-Surge Electric, Inc., contractor, be approved in the amount of $16,100.00. Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 45040-57520, Replace City Circuits. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 0966-19 CO2 Contract 20170006, 2017 Circuit Replacement-Wisconsin Ave.pdf, 2. #0966-19 Resolution

Title

Subject: Communication sponsored by Alder Tate ll, on behalf of Engineering, submitting Change Order No. 2 on Contract 20170006 - 2017 Circuit Replacement - Wisconsin Avenue, Wil-Surge Electric, Inc., contractor.

 

Recommendation of the Public Works and Services Committee on 08-27-19: That Change Order No. 2 on Contract 20170006, 2017 Circuit Replacement - Wisconsin Avenue, Wil-Surge Electric, Inc., contractor, be approved in the amount of $16,100.00.

 

Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 45040-57520, Replace City Circuits.

 

Fiscal Note:  Funds are available as herein delineated.