Title: CHANGE ORDER, CURB AND GUTTER REPLACEMENT CDBG RESOLVED, that Change Order No. 1 on Contract 37-05 (K5-044), Curb & Gutter Replacement C.D.B.G., J.B. Construction Company, contractor, as submitted, be approved in the amount of $9,982.38. FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from the following accounts: $5,611.33 - Account 985.908.5220, Curb & Gutter Replacement $4,371.05 - Account 986.908.5220, Curb 7 Gutter Replacement $9,982.38 - Total FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-1974
Sponsor
Alderman Hart
 
Title
CHANGE ORDER, CURB AND GUTTER REPLACEMENT CDBG
 
 
RESOLVED, that Change Order No. 1 on Contract 37-05 (K5-044), Curb & Gutter Replacement C.D.B.G., J.B. Construction Company, contractor, as submitted, be approved in the amount of $9,982.38.
 
FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$5,611.33 - Account 985.908.5220, Curb & Gutter Replacement
$4,371.05 - Account 986.908.5220, Curb 7 Gutter Replacement
$9,982.38 - Total
 
 