Contract 29-14 (K4-029), City Hall Annex - Boiler Replacement (R1)
Resolved, that Contract 29-14 (K4-029), City Hall Annex - Boiler Replacement (R1), is awarded to Core Mechanical, Inc., Chicago, IL, at its bid price of $527,895.00, it being the lowest responsible bidder.
Fiscal Note: Funding to defray the cost of this public works project should be appropriated from the following accounts:
$214,765.00 - Account 994.200.5030, Annex-Boiler Replacement
$313,130.00 - Account 993.200.5030, Annex-Boiler Replacement
$527,895.00 - Total