File #: 0009-23    Version: A Name: Subject: Communication sponsored by Alder Jones, on behalf of the City Engineer, submitting Change Order No. 1 to Contract 2022010 - Racine and 9th Street Reconstruction, Milwaukee General Construction Co., Contractors. Staff Recommendation to the Publ
Type: Communication Status: Passed
File created: 1/4/2023 In control: Public Works and Services Committee
On agenda: 1/17/2023 Final action: 1/17/2023
Title: Subject: Communication sponsored by Alder Jones, on behalf of the City Engineer, submitting Change Order No. 1 to Contract 2022010 - Racine and 9th Street Reconstruction, Milwaukee General Construction Co., Contractor. Recommendation of the Public Works and Services Committee on 01-10-23: That Change Order No.1 to Contract 2022010- Racine and 9th Street Reconstruction, Milwaukee General Construction Co., Contractors, be approved in the deduct amount of ($7169.89). Fiscal Note: Funding for this change order is credited in the following Org-Object: ($6,314.69) 45040 57500 DPW Paving ($855.20) 60484 57570 Storm Sewers ($7,169.89) Total
Attachments: 1. CCO 1 2022010 Memo, 2. CCO 1 2022010 Signed, 3. #0009-23 Resolution

Title

Subject: Communication sponsored by Alder Jones, on behalf of the City Engineer, submitting Change Order No. 1 to Contract 2022010 - Racine and 9th Street Reconstruction, Milwaukee General Construction Co., Contractor.

 

Recommendation of the Public Works and Services Committee on 01-10-23: That Change Order No.1 to Contract 2022010- Racine and 9th Street Reconstruction, Milwaukee General Construction Co., Contractors, be approved in the deduct amount of ($7169.89).

 

Fiscal Note:  Funding for this change order is credited in the following Org-Object:

($6,314.69) 45040 57500 DPW Paving

($855.20) 60484 57570 Storm Sewers

($7,169.89) Total