Ricine Banner
File #: 0822-16    Version: A Name: Change Order No. 3 on Contract 20150019, Lake Michigan Pathway Phase lll, Ray Hintz, Inc., contractor. (Res No. 0340-16)
Type: Communication Status: Passed
File created: 9/16/2016 In control: Public Works and Services Committee
On agenda: Final action: 10/4/2016
Title: Subject: Change Order No. 3 on Contract 20150019, Lake Michigan Pathway Phase lll, Ray Hintz, Inc., contractor. (Res No. 0340-16) Recommendation of the Public Works and Services Committee on 09-26-16: That Change Order No. 3 on Contract 20150019, Lake Michigan Pathway Phase lll, Ray Hintz, Inc., contractor, as submitted, be approved in the deduct amount of ($76,510.34). Further recommends the below Org-Objects be adjusted in the following amounts. ($15,302.07) - Org-Object 45040-57550, DPW-Lake Michigan Pathway ($61,208.27) - Org-Object 2031-57550, State’s Share Lake MI Pathway ($76,510.34) - Total Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 0822-16 CO 3, Contract 20150019 LMP Phase lll
Related files: Res.0340-16

Title

Subject: Change Order No. 3 on Contract 20150019, Lake Michigan Pathway Phase lll, Ray Hintz, Inc., contractor. (Res No. 0340-16)

 

Recommendation of the Public Works and Services Committee on 09-26-16: That Change Order No. 3 on Contract 20150019, Lake Michigan Pathway Phase lll, Ray Hintz, Inc., contractor, as submitted, be approved in the deduct amount of ($76,510.34).

 

Further recommends the below Org-Objects be adjusted in the following amounts.

 

($15,302.07) - Org-Object 45040-57550, DPW-Lake Michigan Pathway

($61,208.27) - Org-Object 2031-57550, State’s Share Lake MI Pathway

($76,510.34) - Total

 