Title
Subject: (Direct Referral) Communication from the Commissioner of Public Works submitting bid results on Contract 09-14 (K4-009), 2014 Street and Alley Paving - Northside Assessable (R1). (Res. No. 14-0218)
Recommendation of the Public Works and Services Committee on 04-29-14: Deferred
Recommendation of the Public Works and Services Committee on 05-13-14: That Contract 09-14 (K4-009), 2014 Street and Alley Paving - Northside Assessable (R1), be awarded to Milwaukee General Construction Co., Milwaukee, WI, at their bid price of $730,146.14, they being the lowest responsible bidder.
Fiscal Note: Funding to defray the cost of this public works project be appropriated from the following accounts:
$379,616.57 - Account 906.000.5010, Concrete Street Paving
$ 78,555.00 - Account 906.000.5030, Concrete Alley Paving
$ 6,400.00 - Account 906.000.5410, Sanitary Sewer Laterals
$ 10,489.00 - Account 993.908.5010, Concrete Street Paving Misc. Loc.
$138,235.57 - Account 994.908.5010, Concrete Street Paving Misc. Loc.
$ 10,000.00 - Account 994.908.5030, Concrete Alley Paving Mis. Loc.
$ 38,750.00 - Account 287.993.5310, Sanitary Sewer, Var. Loc.
$ 7,000.00 - Account 994.993.5520, Sidewalk Replacement
$ 61,100.00 - Account 104.993.5420, Storm Sewer, Misc. Loc.
$730,146.14 - Total