File #: Res.15-0086    Version: A Name: Final Payment on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1)
Type: Resolution Status: Passed
File created: 3/3/2015 In control: City Attorney's Office
On agenda: Final action: 3/3/2015
Title: Final Payment on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1) Resolved, that the work done by AZAR, LLC., under Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1), is accepted and final payment authorized for a total contract amount of $378,797.58. Fiscal Note: Contract was authorized under Resolution 14-0134, dated April 2, 2014.
Sponsors: Jim Kaplan
Related files: 15-00138
Sponsor
Alderman Kaplan
 
Title
Final Payment on Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1)
 
Resolved, that the work done by AZAR, LLC., under Contract 10-14 (K4-010), 2014 Sidewalk Replacement Program, Phase l (R1), is accepted and final payment authorized for a total contract amount of $378,797.58.
 
Fiscal Note: Contract was authorized under Resolution 14-0134, dated April 2, 2014.