Title:
|
Subject: Consideration of Change Order No. 2 on Contract W-23-6, Water Treatment Filter Rehab Project, Lee Mechanical (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in a net increase of $45,633.00, bringing the contract total to $17,087,223.00.
|