Title: Change Order No. 1 on Contract 15-13 (K3-015), 2013 Alley Paving Phase II Assessable (South) (R1) Resolved, that Change Order No. 1 on Contract 15-13 (K3-015), 2013 Alley Paving Phase II Assessable (South) (R1), LaLonde Contractors, Inc., contractor, is approved in the amount of $49,465.18. Fiscal Note: Funding to defray the cost of this change order be appropriated from the following accounts: $14,465.18 - Account 906.000.5030, Conc. Alley Pav. Misc. (2013 Budget) $35,000.00 - Account 993.908.5030, Conc. Alley Pav. Misc. (2013 Budget) $49,465.18 - Total
Sponsors: Jim Kaplan
Related files: 14-10064
Sponsor
Alderman Kaplan
 
Title
Change Order No. 1 on Contract 15-13 (K3-015), 2013 Alley Paving Phase II Assessable (South) (R1)
 
Resolved, that Change Order No. 1 on Contract 15-13 (K3-015), 2013 Alley Paving Phase II Assessable (South) (R1), LaLonde Contractors, Inc., contractor, is approved in the amount of $49,465.18.
 
Fiscal Note: Funding to defray the cost of this change order be appropriated from the following accounts:
 
$14,465.18      -      Account 906.000.5030, Conc. Alley Pav. Misc. (2013 Budget)
$35,000.00      -      Account 993.908.5030, Conc. Alley Pav. Misc. (2013 Budget)
$49,465.18       -       Total