Sponsor
Alderman Maack
Title
Change Order and Final Payment for New Football Lighting at Horlick Athletic Field
Resolved, that Change Order #1 on Contract 59-05 (K5-068), New Football Lighting at Horlick Athletic Field, Delta Electric, Inc., Racine, contractor, be approved in the increased amount of $1,647.00, and that the work be accepted and final payment be authorized in the amount of $244,017.00 from funds heretofore appropriated.
Fiscal Note: Final payment be authorized in the amount of $244,017.00 from Account 985.710.5050, Horlick Field Lights.