Ricine Banner
File #: Res.07-0081    Version: A Name: Change Order No. 4 on contact for Lake Michigan Pathway, Phase II
Type: Resolution Status: Passed
File created: 2/21/2007 In control: City Attorney's Office
On agenda: Final action: 2/21/2007
Title: Change Order No. 4 on Contact for Lake Michigan Pathway, Phase II Resolved, that Change Order No. 4 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $33,412.53. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $11,310.74 - Account 104.986.5420, Storm Sewers, Various Locations $ 15.84 - Account 985.913.5090, Goold @ Michigan Slope Stabilization $ 4,593.89 - Account 986.908.5520, Sidewalk Replacement $ 8,700.23 - Account 986.908.5130, Asphalt Resurfacing $ 8,791.83 - Account 930.021.5810, CMAQ - Lake Michigan Pathway, Phase II $33,412.53 Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 07-0157
Sponsor
Alderman Hart
 
Title
Change Order No. 4 on Contact for Lake Michigan Pathway, Phase II
 
 
Resolved, that Change Order No. 4 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $33,412.53.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$11,310.74 - Account 104.986.5420, Storm Sewers, Various Locations
$        15.84 - Account 985.913.5090, Goold @ Michigan Slope Stabilization
$  4,593.89 - Account 986.908.5520, Sidewalk Replacement
$  8,700.23 - Account 986.908.5130, Asphalt Resurfacing
$  8,791.83 - Account 930.021.5810, CMAQ - Lake Michigan Pathway, Phase II
$33,412.53
 
 
Fiscal Note: Funds are available as herein delineated.