Title: CHANGE ORDER FOR RACINE STREET SANITARY SEWER LINING RESOLVED, that Change Order No. 1 on Contract 2-06 (K6-002), Racine Street Sanitary Sewer Lining, Visu-Sewer Clean & Seal, contractor, as submitted, be approved in the amount of $5,407.00. FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 986.907.5610, Sanitary Sewer Construction, Various Locations. FURTHER RESOLVED, that a time extension, until October 31, 2006, be approved. FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-2098
Sponsor
Alderman Hart
 
Title
CHANGE ORDER FOR RACINE STREET SANITARY SEWER LINING
 
 
RESOLVED, that Change Order No. 1 on Contract 2-06 (K6-002), Racine Street Sanitary Sewer Lining, Visu-Sewer Clean & Seal, contractor, as submitted, be approved in the amount of $5,407.00.
 
FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 986.907.5610, Sanitary Sewer Construction, Various Locations.
 
FURTHER RESOLVED, that a time extension, until October 31, 2006, be approved.
 
 
FISCAL NOTE: Funds are available as herein delineated.