Title
Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/ Engineering submitting Change Order No. 1 on Contract 49-05 (K5-056), Lake Michigan Pathway Phase II, Bane-Nelson, contractor.
Recommendation: Change Order No. 1 on Contract 49-05 (K5-056, Lake Michigan Pathway Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $58,718.39.
Further recommends that funding to defray the cost of this change order be appropriated from the following accounts:
$28,276.50 - Account 986.913.5080, Lake Michigan Pathway
$27,812.96 - Account 731.000.5970, Kewaunee Street Demolition
$ 2,628.93 - Account 104.985.5420, Storm Sewer, Various Locations
$58,718.39 - Total
Fiscal Note: Funds are available as herein delineated.