Title: Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor, be approved Resolved, that Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor, as submitted, be approved in the deduct amount of $2,820.80. Further resolved, that Account 104.989.5420, Storm Sewers-Miscellaneous Locations, be adjusted by deducting $2,820.80. FISCAL NOTE: Change Order No. 1 will result in a decrease in contract price.
Sponsors: Gregory Helding
Related files: 10-5820
Sponsor
Alderman Helding
 
Title
Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor, be approved
 
Resolved, that Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor, as submitted, be approved in the deduct amount of $2,820.80.
 
Further resolved, that Account 104.989.5420, Storm Sewers-Miscellaneous Locations, be adjusted by deducting $2,820.80.
 
FISCAL NOTE:  Change Order No. 1 will result in a decrease in contract price.