Ricine Banner
File #: 08-1671    Version: A Name: Change Order No. 2 on Contract 26-07 (K7-030), 2007 City Resurfacing
Type: Communication Status: Passed
File created: 1/21/2008 In control: Public Works and Services Committee
On agenda: Final action: 2/5/2008
Title: Subject: Direct Referral. Communication from the Commissioner of Public Works submitting Change Order No. 2 on Contract 26-07 (K7-030), 2007 City Resurfacing, A. W. Oakes & Son, contractor. Recommendation: Change Order No. 2 on Contract 26-07 (K7-030), 2007 City Resurfacing, A. W. Oakes & Son, contractor, as submitted, be approved in the amount of $62,956.81. Further recommends that funding to defray the cost of this change order be appropriated from Account 987.907.5310, Sanitary Sewer Construction. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. Ald Hart - CO 2-26-07, 2. CO #2-26-07
Related files: Res.08-0619

Title

Subject:  Direct Referral.  Communication from the Commissioner of Public Works submitting Change Order No. 2 on Contract 26-07 (K7-030), 2007 City Resurfacing, A. W. Oakes & Son, contractor.

 

Recommendation: Change Order No. 2 on Contract 26-07 (K7-030), 2007 City Resurfacing, A. W. Oakes & Son, contractor, as submitted, be approved in the amount of $62,956.81.

 

Further recommends that funding to defray the cost of this change order be appropriated from Account 987.907.5310, Sanitary Sewer Construction.

 

Fiscal Note: Funds are available as herein delineated.