Ricine Banner
File #: Res.07-0147    Version: A Name: Change Order No. 3 for upgrades at Community Centers
Type: Resolution Status: Passed
File created: 4/4/2007 In control: City Attorney's Office
On agenda: Final action: 4/4/2007
Title: Change Order No. 3 for upgrades at Community Centers Resolved, that Change Order No. 3 on Contract 44-06 (K6-046), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor, as submitted, be approved in the amount of $11,828.00. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $ 9,289.00 - Account 987.640.5010, Tyler Domer BAS $ 2,539.00 - Account 987.660.5010, MLK BAS. $11,828.00 Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 07-0381

Sponsor

Alderman Hart

 

Title

Change Order No. 3 for upgrades at Community Centers

 

 

Resolved, that Change Order No. 3 on Contract 44-06 (K6-046), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor, as submitted, be approved in the amount of $11,828.00.

 

Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:

 

$  9,289.00 - Account 987.640.5010, Tyler Domer BAS

$  2,539.00 - Account 987.660.5010, MLK BAS.

$11,828.00

 

 