Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering requesting to rescind Res. 08-0851 and create a new resolution for Change Order No. 4 to Contract 20-07 (K7-023), Local Road Improvement Program, Cornerstone Pavers, contractor. (Res.08-1053)
Recommendation of the Public Works and Services Committee on 10-14-08: That Resolution 08-0851, dated June 3, 2008, be rescinded.
Further recommends that Change Order No. 4 to Contract 20-07 (K7-023), Local Road Improvement Program, Cornerstone Pavers, contractor, be approved in the amount of $7,658.99.
Further recommends that funding to defray the cost of this change order be appropriated from Account 986.908.5010, Miscellaneous Concrete Paving.