File #: 10-5820    Version: A Name: Change Order No. 1 on Contract 36-09(K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor
Type: Communication Status: Passed
File created: 11/18/2010 In control: Public Works and Services Committee
On agenda: Final action: 12/7/2010
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor. (Res.10-2305) Recommendation of the Public Works and Services Committee on 11-30-10: That Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor, as submitted, be approved in the deduct amount of $2,820.80. Further recommends that Account 104.989.5420, Storm Sewers-Miscellaneous Locations, be adjusted by deducting $2,820.80. Fiscal Note: Change Order No. 1 will result in a decrease in contract price.
Attachments: 1. 10-5820, 2. 36-09
Related files: Res.10-2305
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor.  (Res.10-2305)
 
Recommendation of the Public Works and Services Committee on 11-30-10: That Change Order No. 1 on Contract 36-09 (K9-037), Colonial Park Streambank Stabilization, Conservation Land Stewardship, Inc., contractor, as submitted, be approved in the deduct amount of $2,820.80.
 
Further recommends that Account 104.989.5420, Storm Sewers-Miscellaneous Locations, be adjusted by deducting $2,820.80.
 
Fiscal Note:  Change Order No. 1 will result in a decrease in contract price.