File #: Res.10-1945    Version: A Name: Contract 16-10 (K0-016), 2010 Sidewalk Replacement - Phase I, be awarded to AZAR, LLC, at its bid price
Type: Resolution Status: Passed
File created: 4/7/2010 In control: City Attorney's Office
On agenda: Final action: 4/7/2010
Title: Contract 16-10 (K0-016), 2010 Sidewalk Replacement - Phase I, be awarded to AZAR, LLC, at its bid price Resolved, that Contract 16-10 (K0-016), 2010 Sidewalk Replacement-Phase I, be awarded to AZAR, LLC, Racine, WI, at its bid price of $142,245.70, it being the lowest responsible bidder. Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts: $132,245.70 - Account 906.000.5520, Sidewalk Replacement $ 10,000.00 - Account 990.908.5520, Sidewalk Replacement $142,245.70 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 10-4878
Sponsor
Alderman Helding
 
Title
Contract 16-10 (K0-016), 2010 Sidewalk Replacement - Phase I, be awarded to AZAR, LLC, at its bid price
 
Resolved, that Contract 16-10 (K0-016), 2010 Sidewalk Replacement-Phase I, be awarded to AZAR, LLC, Racine, WI, at its bid price of $142,245.70, it being the lowest responsible bidder.
 
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
 
$132,245.70 - Account 906.000.5520, Sidewalk Replacement
$  10,000.00 - Account 990.908.5520, Sidewalk Replacement
$142,245.70 - Total
 
Fiscal Note:  Funds are available as herein delineated.