Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 2 on Contract 12-07 (K7-012), Asphalt Paving, C.D.B.G., Payne & Dolan, Inc., contractor. Recommendation: That Change Order No. 2 on Contract 12-07 (K7-012), Asphalt Paving, C.D.B.G., Payne & Dolan, Inc., contractor, as submitted, be approved in the amount of $4,249.75. Further recommends that funding to defray the cost of this change order be appropriated from the following accounts: $2,449.75 - Account 104.988.5420, Storm Sewers, Misc. Loc. $1,800.00 - Account 987.908.5130, Asphalt Resurfacing $4,249.75 - Total Fiscal Note: Funds are available as herein delineated.
Attachments: 1. CO #2-12-07, 2. Ald Hart - CO 2-12-07
Related files: Res.08-0594
Title
Subject: Direct Referral.  Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 2 on Contract 12-07 (K7-012), Asphalt Paving, C.D.B.G., Payne & Dolan, Inc., contractor.
 
Recommendation: That Change Order No. 2 on Contract 12-07 (K7-012), Asphalt Paving, C.D.B.G., Payne & Dolan, Inc., contractor, as submitted, be approved in the  amount of $4,249.75.
 
Further recommends that funding to defray the cost of this change order be appropriated from the following accounts:
 
$2,449.75 - Account 104.988.5420, Storm Sewers, Misc. Loc.
$1,800.00 - Account 987.908.5130, Asphalt Resurfacing
$4,249.75 - Total
 