Ricine Banner
File #: 13-9181    Version: A Name: Final payment on Contract 46-12 (K2-056), Festival Hall Roof Replacement (R1), Carlson Racine Roofing & Sheet Metal, Inc., contractor. (Res. No. 13-0315)
Type: Communication Status: Passed
File created: 7/22/2013 In control: Public Works and Services Committee
On agenda: Final action: 8/5/2013
Title: Subject: (Direct Referral) Communication from the Commissioner of Public Works submitting a request for final payment on Contract 46-12 (K2-056), Festival Hall Roof Replacement (R1), Carlson Racine Roofing & Sheet Metal, Inc., contractor. (Res. No. 13-0315) Recommendation of the Public Works and Services Committee on 7-30-13: That the work done by Carlson Racine Roofing & Sheet Metal, Inc. under Contract 46-12 (K2-056), Festival Hall Roof Replacement (R1), be accepted and final payment authorized for a total contract amount of $544,150.00. Fiscal Note: Contract was authorized under Resolution No. 12-3227, dated July 17, 2012.
Attachments: 1. 46-12 final payment.pdf
Related files: Res.13-0315
Title
Subject: (Direct Referral) Communication from the Commissioner of Public Works submitting a request for final payment on Contract 46-12 (K2-056), Festival Hall Roof Replacement (R1), Carlson Racine Roofing & Sheet Metal, Inc., contractor. (Res. No. 13-0315)
 
Recommendation of the Public Works and Services Committee on 7-30-13: That the work done by Carlson Racine Roofing & Sheet Metal, Inc. under Contract 46-12 (K2-056), Festival Hall Roof Replacement (R1), be accepted and final payment authorized for a total contract amount of $544,150.00.
 
Fiscal Note: Contract was authorized under Resolution No. 12-3227, dated July 17, 2012.