Sponsor
Alderman Helding
Title
Change Order No. 1 to Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR LLC., contractor, be approved
Resolved, that Change Order No. 1 to Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR LLC, contractor, as submitted, be approved that will provide a time extension until July 1, 2011 to complete this contract.
FISCAL NOTE: There will be no change in contract price as a result of this change order.