Ricine Banner
File #: Res.10-2122    Version: A Name: Change Order No. 4 to Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor, be approved
Type: Resolution Status: Passed
File created: 8/2/2010 In control: City Attorney's Office
On agenda: Final action: 8/2/2010
Title: Change Order No. 4 to Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor, be approved Resolved, that Change Order No. 4 on Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor, be approved in the amount of $3,136.72. Further resolved, that funding to defray the cost of this change order be appropriated from Account 990.220.5030, CHP-Structural Repairs. Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 10-5352
Sponsor
Alderman Helding
 
Title
Change Order No. 4 to Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor, be approved
 
Resolved, that Change Order No. 4 on Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor, be approved in the amount of $3,136.72.
 
Further resolved, that funding to defray the cost of this change order be appropriated from Account 990.220.5030, CHP-Structural Repairs.
 
Fiscal Note:  Funds are available as herein delineated.