Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/City Engineer submitting Change Order No. 1 on Contract 24-13 (K3-024), 2013 CDBG Asphalt, Payne & Dolan, Inc., contractor. (Res. No. 14-0092)
Recommendation of the Public Works and Services Committee on 02-26-14: That Change Order No. 1 on Contract 24-13 (K3-024), 2013 CDBG Asphalt, Payne & Dolan, Inc., contractor, be approved in the amount of $115,131.45.
Further recommends that funding to defray the cost of this change order be appropriated from the following accounts:
$100,000.00 - Account 893.030.5540, Asphalt Resurfacing CDBG
$ 15,131.45 - Account 287.994.5310, Sanitary Sewer Var Locs
$115,131.45 - Total