File #: 0212-22    Version: A Name: Subject: Communication sponsored by Alder Jones, on behalf of the City Engineer, submitting Change Order No. 2 to Contract 2021003 - Sidewalk Replacement-Phase I (RWP), Forward Contractors, Contractor. Staff Recommendation to the Public Works and Servi
Type: Communication Status: Passed
File created: 4/6/2022 In control: Public Works and Services Committee
On agenda: Final action: 5/3/2022
Title: Subject: Communication sponsored by Alder Jones, on behalf of the City Engineer, submitting Change Order No. 2 to Contract 2021003 - Sidewalk Replacement-Phase I (RWP), Forward Contractors, Contractor. Staff Recommendation to the Public Works and Services Committee on 04-12-22: That Change Order No.2 to Contract 2021003 - Sidewalk Replacement-Phase I (RWP), Forward Contractors, Contractor, be approved in the deduct of ($143,485.10). Fiscal Note: Funding for this change order is credited in the following Org-Objects and includes an RWP penalty of ($13,713.00) ($375.81) 45040 57515 Sidewalks ($137,053.79) 40104 57515 Sidewalk Assessment ($6,055.50) Net Penalties ($143,485.10) Total
Attachments: 1. CO2 Memo 2021003 revised 2 with RWP, 2. CO 2 2021003 revised with RWP, 3. #0212-22 Resolution

Title

Subject: Communication sponsored by Alder Jones, on behalf of the City Engineer, submitting Change Order No. 2 to Contract 2021003 - Sidewalk Replacement-Phase I (RWP), Forward Contractors, Contractor.

 

Staff Recommendation to the Public Works and Services Committee on 04-12-22: That Change Order No.2 to Contract 2021003 - Sidewalk Replacement-Phase I (RWP), Forward Contractors, Contractor, be approved in the deduct of ($143,485.10).

 

Fiscal Note: Funding for this change order is credited in the following Org-Objects and includes an RWP penalty of ($13,713.00)

($375.81) 45040 57515 Sidewalks

($137,053.79) 40104 57515 Sidewalk Assessment

($6,055.50) Net Penalties

($143,485.10) Total