Title: Change Order No. 1 on Contract 14-13 (K3-014), Alley Paving Phase I Assessable (R1) Resolved, that Change Order No. 1 on Contract 14-13 (K3-014), Alley Paving Phase I Assessable (R1), LaLonde Contractors, Inc., contractor, is approved in the amount of $24,172.09. Fiscal Note: Funding to defray the cost of this change order be appropriated from the following accounts: $16,815.80 - Account 906.000.5030, Concrete Alley Paving Misc. $ 7,356.29 - Account 993.908.5030, Concrete Alley Paving Misc. $24,172.09 - Total
Sponsors: Sandy Weidner
Related files: 14-9891
Sponsor
Alderman Weidner
 
Title
Change Order No. 1 on Contract 14-13 (K3-014), Alley Paving Phase I Assessable (R1)
 
Resolved, that Change Order No. 1 on Contract 14-13 (K3-014), Alley Paving Phase I Assessable (R1), LaLonde Contractors, Inc., contractor, is approved in the amount of $24,172.09.
 
Fiscal Note: Funding to defray the cost of this change order be appropriated from the following accounts:
 
$16,815.80      -      Account 906.000.5030, Concrete Alley Paving Misc.
$ 7,356.29      -      Account 993.908.5030, Concrete Alley Paving Misc.
$24,172.09       -       Total