File #: Res.11-2501    Version: A Name: Change Order No. 4 on Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor, be approved
Type: Resolution Status: Passed
File created: 4/18/2011 In control: City Attorney's Office
On agenda: Final action: 4/18/2011
Title: Change Order No. 4 on Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor, be approved Resolved, that Change Order No. 4 on Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor, be approved in the amount of $7,600.00 Further resolved, that funding to defray the cost of this change order be appropriated from Account 930.077.5810, State Street Lift Bridge Repairs. Further resolved, that a time extension be approved until April 29, 2011 to complete this contract. Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 11-6253
Sponsor
Alderman Helding
 
Title
Change Order No. 4 on Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor, be approved
 
Resolved, that Change Order No. 4 on Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor, be approved in the amount of $7,600.00
 
Further resolved, that funding to defray the cost of this change order be appropriated from Account 930.077.5810, State Street Lift Bridge Repairs.
 
Further resolved, that a time extension be approved until April 29, 2011 to complete this contract.
 
Fiscal Note:  Funds are available as herein delineated.