Ricine Banner
File #: Res.08-0848    Version: A Name: Change Order on contract for BUS Administrative Office Expansion, Absolute Construction
Type: Resolution Status: Passed
File created: 6/3/2008 In control: City Attorney's Office
On agenda: Final action: 6/3/2008
Title: Change Order on contract for BUS Administrative Office Expansion, Absolute Construction Resolved, that Change Order No. 1 on Contract 02-08 (K8-002), Belle Urban System Administrative Office Expansion, Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $59,014.00. Further resolved, that funding to defray the cost of this change order be appropriated from Account No. 105.900.5010, Capital Projects. Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 08-2222
Sponsor
Alderman Helding
 
Title
Change Order on contract for BUS Administrative Office Expansion, Absolute Construction
 
Resolved, that Change Order No. 1 on Contract 02-08 (K8-002), Belle Urban System  Administrative Office Expansion, Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $59,014.00.
 
Further resolved, that funding to defray the cost of this change order be appropriated from Account No. 105.900.5010, Capital Projects.
 
Fiscal Note: Funds are available as herein delineated.