File #:
|
05-1118
Version:
A
|
Name:
|
Change Order No. 1 on Contract 36-05 (K5-043), 2005 City Resurfacing, Payne & Dolan, Inc., contractor.
|
Type:
|
Communication
|
Status:
|
Passed
|
On agenda:
|
|
Final action:
|
11/1/2005
|
Title:
|
Subject: DIRECT REFERRAL. Communication from the City Engineer submitting Change Order No. 1 on Contract 36-05 (K5-043), 2005 City Resurfacing, Payne & Dolan, Inc., contractor.
Recommendation: Change Order No. 1 on Contract 36-05 (K5-043), 2005 City Resurfacing, Payne & Dolan, Inc., contractor, as submitted, be approved in the amount of $4,450.00.
Further recommends that funding to defray to the cost of this change order be appropriated from the following accounts:
$ 221.08 - Account 983.908.5020, Concrete Pavement Repl.-Misc.
$4,228.92 - Account 985.913.5010, Environmental Remediation
$4,450.00
Fiscal Note: Funds are available as herein delineated.
|
Title
Subject: DIRECT REFERRAL. Communication from the City Engineer submitting Change Order No. 1 on Contract 36-05 (K5-043), 2005 City Resurfacing, Payne & Dolan, Inc., contractor.
Recommendation: Change Order No. 1 on Contract 36-05 (K5-043), 2005 City Resurfacing, Payne & Dolan, Inc., contractor, as submitted, be approved in the amount of $4,450.00.
Further recommends that funding to defray to the cost of this change order be appropriated from the following accounts:
$ 221.08 - Account 983.908.5020, Concrete Pavement Repl.-Misc.
$4,228.92 - Account 985.913.5010, Environmental Remediation
$4,450.00
Fiscal Note: Funds are available as herein delineated.
|