File #: Res.09-1196    Version: A Name: Change Order on contract for City Hall Renovations - Phase II, Absolute Construction
Type: Resolution Status: Passed
File created: 1/20/2009 In control: City Attorney's Office
On agenda: Final action: 1/20/2009
Title: Change Order on contract for City Hall Renovations - Phase II, Absolute Construction Resolved, that Change Order No. 1 on Contract 53-08 (K8-061), City Hall Renovations - Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $40,292.00. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $14,838.21 - Account 989.100.5010, City Hall-Facilities Plan Implementation $23,353.79 - Account 987.100.5010, City Hall Renovations-Phase II $ 2,100.00 - Account 101.191.5760, Finance Dept. Building Improvements $40,292.00 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 08-3060

Sponsor

Alderman Helding

 

Title

Change Order on contract for City Hall Renovations - Phase II, Absolute Construction

 

Resolved, that Change Order No. 1 on Contract 53-08 (K8-061), City Hall Renovations - Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $40,292.00.

 

Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:

 

$14,838.21 - Account 989.100.5010, City Hall-Facilities Plan Implementation

$23,353.79 - Account 987.100.5010, City Hall Renovations-Phase II

$  2,100.00 - Account 101.191.5760, Finance Dept. Building Improvements

$40,292.00 - Total

 

Fiscal Note: Funds are available as herein delineated.