Resolved, that Contract 45-10 (K0-054), Solid Waste Garage Tuckpointing, be awarded to AZAR LLC, Racine, WI, at its bid price of $48,070.00, plus Alternate Bid #1 in the amount of $4,180.00, for a total contract amount of $52,250.00, it being the lowest responsible bidder.
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
$24,075.72 - Account 989.410.5010, Solid Waste Garage Insulation
$28,174.28 - Account 990.410.5010, Solid Waste Garage Tuckpointing
$52,250.00 - Total
Fiscal Note: Funds are available as herein delineated.
|
Sponsor
Alderman Helding
Title
Contract 45-10 (K0-054), Solid Waste Garage Tuckpointing, be awarded to AZAR, LLC
Resolved, that Contract 45-10 (K0-054), Solid Waste Garage Tuckpointing, be awarded to AZAR LLC, Racine, WI, at its bid price of $48,070.00, plus Alternate Bid #1 in the amount of $4,180.00, for a total contract amount of $52,250.00, it being the lowest responsible bidder.
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
$24,075.72 - Account 989.410.5010, Solid Waste Garage Insulation
$28,174.28 - Account 990.410.5010, Solid Waste Garage Tuckpointing
$52,250.00 - Total