File #: 08-2839    Version: A Name: Change Order No. 1 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays
Type: Communication Status: Passed
File created: 10/23/2008 In control: Public Works and Services Committee
On agenda: Final action: 11/18/2008
Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/ Engineering submitting Change Order No. 1 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, contractor. (Res.08-1103) Recommendation of the Public Works and Services Committee on 11-11-08: That Change Order No. 1 on Contract 4-08 (K8-004), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, Inc., contractor, as submitted, be approved in the amount of $6,480.00. Further recommends that funding to defray the cost of this change order be appropriated from the Racine Water Utility. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. Ald Helding - CO 1-44-08, 2. CO #1-44-08
Related files: Res.08-1103
Title
Subject:  Direct Referral.  Communication from the Assistant Commissioner of Public Works/ Engineering submitting Change Order No. 1 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, contractor.  (Res.08-1103)
 
Recommendation of the Public Works and Services Committee on 11-11-08: That Change Order No. 1 on Contract 4-08 (K8-004), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, Inc., contractor, as submitted, be approved in the amount of $6,480.00.
 
Further recommends that funding to defray the cost of this change order be appropriated from the Racine Water Utility.
 
Fiscal Note:      Funds are available as herein delineated.