Sponsor
Alderman Helding
Title
Change Order for Sixth Street Utility Construction
Resolved, that Change Order No. 1 on Contract 3-08 (K8-003), Sixth Street Utility Construction (R1), Globe Contractors, Inc., contractor, as submitted, be approved in the amount of $11,916.50.
Further resolved, that funding to defray the cost of this change order be appropriated from the Racine Water Utility.
Fiscal Note: Funds are available as herein delineated.