Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 3 to Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR LLC, contractor. (Res.11-2595)
Recommendation of the Public Works and Services Committee on 5-31-11: That Change Order No. 3 on Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR, LLC, contractor, be approved in the amount of $13,734.13.
Further recommends that funding to defray the cost of this change order be appropriated from Account 990.100.5020, City Hall Tuckpointing.
Fiscal Note: Funds are available as herein delineated.