Sponsor
Alderman Weidner
Title
Change Order No. 1 on Contract 38-12 (K2-043)
Resolved, that Change Order No. 1 on Contract 38-12 (K2-043), Sewer & Lateral Lining, Musson Brothers, Inc., contractor, as submitted, is approved that will provide a time extension until October 19, 2012 to complete this contract.
Fiscal Note: There will be no change in contract price as a result of this change order.