Subject: Final Payment on Contract 20170043, 2017 Sanitary Sewer and Lateral Lining, Musson Brothers, Inc., contractor. (Res. 0348-18)
Recommendation of the Public Works and Services Committee on 10-30-18: That the work done by Musson Brothers, Inc., under contract 20170043, 2017 Sanitary Sewer and Lateral Lining, be accepted and final payment authorized for a total contract amount of $1,600,201.50. Final Payment to include retainage.