File #:
|
Res.09-1510
Version:
A
|
Name:
|
Bid for Contract 50-09 (K9-051), Parks and Parking System Improvement Project (R1), be awarded to O&M Excavation & Grading, Inc., of Union Grove,WI
|
Type:
|
Resolution
|
Status:
|
Passed
|
On agenda:
|
|
Final action:
|
7/21/2009
|
Title:
|
Bid for Contract 50-09 (K9-051), Parks and Parking System Improvement Project (R1), be awarded to O&M Excavation & Grading, Inc., of Union Grove,WI
Resolved, that the base bid of O&M Excavation & Grading, Inc. of Union Grove, WI for Contract 5-09 (K9-051), Parks and Parking System Improvements Project (R1), be accepted for a total bid amount of $409,861.23.
Fiscal Note: Funding is available from the following accounts:
988.700.5020, Lincoln Parking Lot Asphalt, $10, 854.90
988.700.5030, Lockwood Parking Lot Asphalt, $158,348.75
988.740.5020, Blacktop Paths through Zoo, $12,326.00
106.989.5750, Land Improvements, Parking Lot Repairs, $15,519.70
107.000.5750, Golf Land Improvements-Johnson Parking Lot, $109,905.18
207.000.5750, Cemetery Land Improvement - Roads and Walks 2008, $24,399.00
207.000.5750, Cemetery Land Improvement - Roads and Walks 2009, $29,785.30
989.690.5010, Lakeview Basketball Court, $19,055.40
989.740.5010, Blacktop Paths through Zoo, $11,755.35
786.000.5900, Lockw...
|
Sponsor
Alderman Wisneski
Title
Bid for Contract 50-09 (K9-051), Parks and Parking System Improvement Project (R1), be awarded to O&M Excavation & Grading, Inc., of Union Grove,WI
Resolved, that the base bid of O&M Excavation & Grading, Inc. of Union Grove, WI for Contract 5-09 (K9-051), Parks and Parking System Improvements Project (R1), be accepted for a total bid amount of $409,861.23.
Fiscal Note: Funding is available from the following accounts:
988.700.5020, Lincoln Parking Lot Asphalt, $10, 854.90
988.700.5030, Lockwood Parking Lot Asphalt, $158,348.75
988.740.5020, Blacktop Paths through Zoo, $12,326.00
106.989.5750, Land Improvements, Parking Lot Repairs, $15,519.70
107.000.5750, Golf Land Improvements-Johnson Parking Lot, $109,905.18
207.000.5750, Cemetery Land Improvement - Roads and Walks 2008, $24,399.00
207.000.5750, Cemetery Land Improvement - Roads and Walks 2009, $29,785.30
989.690.5010, Lakeview Basketball Court, $19,055.40
989.740.5010, Blacktop Paths through Zoo, $11,755.35
786.000.5900, Lockwood Basketball Court, $17,911.65
|