Change Order No. 2 to Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II, AZAR LLC., be approved
Resolved, that Change Order No. 2 to Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II, AZAR LLC, contractor, as submitted, be approved that will provide a time extension until November 13, 2009 to complete this contract.
Fiscal Note: There will be no change in contract price as a result of this change order.