File #: 0904-24    Version: A Name: Subject: Change Order No. 3 on Contract W-24-1, 2024 Lead Service Replacements - Phase 2, Miller Pipeline, LLC (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an overall net decrease of $88,777.92, bringing the
Type: Communication Status: Passed
File created: 10/7/2024 In control: Waterworks Commission
On agenda: Final action: 10/17/2024
Title: Subject: Change Order No. 3 on Contract W-24-1, 2024 Lead Service Replacements - Phase 2, Miller Pipeline, LLC (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an overall net decrease of $88,777.92, bringing the total contract amount to $913,857.21.
Attachments: 1. co#3_w-24-1_ltr to commsrs

Title

Subject: Change Order No. 3 on Contract W-24-1, 2024 Lead Service Replacements - Phase 2, Miller Pipeline, LLC (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an overall net decrease of $88,777.92, bringing the total contract amount to $913,857.21.