Title
Subject: Direct Referral, Change Order #2 Contract 52-07 (K7-061), Remodel Racine Zoological Gardens, Phase III, by Seater Construction Co., Inc. (Res. #08-0770)
Recommendation of the Public Safety and Licensing Committee on 4-21-08: That Change Order #2 Contract 52-07 (K7-061), Remodel Racine Zoological Gardens, Phase III, by Seater Construction Co., Inc. be approved.
Fiscal Note: Funds are available in account 987.740.5030, Entrance Complex/Parking, $293,266.00 for the City's portion of the project. The remaining funds will be provided by the Racine Zoological Society.