File #: 08-2910    Version: A Name: Change Order No. 2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays
Type: Communication Status: Passed
File created: 11/12/2008 In control: Public Works and Services Committee
On agenda: Final action: 12/16/2008
Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/ Engineering submitting Change Order No. 2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A.W. Oakes & Son, contractor. (Res.08-1170) Recommendation of the Public Works and Services Committee on 11-25-08: Defer Recommendation of the Public Works and Services Committee on 12-9-08: That Change Order No.2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, contractor, be approved, in the credit amount of $5,400.00. Further recommend that the completion date be extended to December 3, 2008. Fiscal Note: The contract amount was decreased due to the withholding of liquidated damages for completing the project after the original completion date of November 5, 2008.
Attachments: 1. Ald Helding - CO 2-44-08, 2. CO #2-44-08
Related files: Res.08-1170
Title
Subject: Direct Referral.  Communication from the Assistant Commissioner of Public Works/ Engineering submitting Change Order No. 2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A.W. Oakes & Son, contractor.  (Res.08-1170)
 
Recommendation of the Public Works and Services Committee on 11-25-08: Defer
 
Recommendation of the Public Works and Services Committee on 12-9-08: That Change Order No.2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, contractor, be approved, in the credit amount of $5,400.00.
 
Further recommend that the completion date be extended to December 3, 2008.
 