Legislation Details

File #: 0724-26    Version: A Name: Subject: Consideration of Change Order #2 on Contract W-25-6, STH 31 Water Main Replacement, A.W. Oakes & Son (Contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $564,758, bringing the total contract
Type: Communication Status: In Committee
File created: 8/10/2026 In control: Waterworks Commission
On agenda: Final action:
Title: Subject: Consideration of Change Order #2 on Contract W-25-6, STH 31 Water Main Replacement, A.W. Oakes & Son (Contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $564,758, bringing the total contract amount to $2,821,328.
Attachments: 1. 2026.0819 - Waterworks Change Order Memo - W-25-6 CO#2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Subject: Consideration of Change Order #2 on Contract W-25-6, STH 31 Water Main Replacement, A.W. Oakes & Son (Contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an increase of $564,758, bringing the total contract amount to $2,821,328.