Ricine Banner
File #: Res.11-2438    Version: A Name: Permission granted to the Interim Commissioner of Public Works/City Engineer to apply for and accept a Focus on Energy LED Streetlight Retrofit Grant from WE Energies
Type: Resolution Status: Passed
File created: 3/15/2011 In control: City Attorney's Office
On agenda: Final action: 3/15/2011
Title: Permission granted to the Interim Commissioner of Public Works/City Engineer to apply for and accept a Focus on Energy LED Streetlight Retrofit Grant from WE Energies Resolved, that permission be granted to the Interim Commissioner of Public Works/City Engineer to apply for and accept a Focus on Energy Grant (Grant Control No. 2011-005) from WE Energies for upgrading street light fixtures on various circuits throughout the City of Racine with more energy efficient LED lighting. Fiscal Note: The estimated project cost is $107,718.00 and will result in an annual electric cost savings of $18,719.00. The grant is in the amount of $5,911.00, resulting in an estimated 5.4-year payback. Funds for the project are available in the 2011 Street Lighting Capital Outlay and CDBG-R Program.
Sponsors: James Spangenberg
Related files: 11-6104
Sponsor
Alderman Spangenberg
 
Title
Permission granted to the Interim Commissioner of Public Works/City Engineer to apply for and accept a Focus on Energy LED Streetlight Retrofit Grant from WE Energies
 
Resolved, that permission be granted to the Interim Commissioner of Public Works/City Engineer to apply for and accept a Focus on Energy Grant (Grant Control No. 2011-005) from WE Energies for upgrading street light fixtures on various circuits throughout the City of Racine with more energy efficient LED lighting.
 
Fiscal Note:  The estimated project cost is $107,718.00 and will result in an annual electric cost savings of $18,719.00.  The grant is in the amount of $5,911.00, resulting in an estimated 5.4-year payback.  Funds for the project are available in the 2011 Street Lighting Capital Outlay and CDBG-R Program.